Marks and Spencer - Watford Cross
Marks and Spencer is a major British multinational retailer specialising in the selling of clothing, home furnishings and luxury food products. The company was established in 1884.
- Location
- Watford
- Value
- £449,740
- Started
- July 2014
- Completed
- September 2014
- Category
- Projects
The work
Rossair was engaged to remove and replace R22 air conditioning units across M&S locations nationwide. The Watford installation involved replacing a roof-mounted chiller and refurbishing four air-conditioning handling units along with their controls and supporting systems.
R22 was the standard refrigerant in commercial air conditioning for decades, but it damages the ozone layer. From 1 January 2015 it became illegal to service or top up a system with R22, including recycled or reclaimed gas, so R22 plant that developed a fault after that date could not be recharged and returned to service. The Watford works were completed in September 2014, ahead of that deadline.
Documentation provided upon completion included operations and maintenance manuals and as-installed drawings.
Areas of expertise
- R22 plant removal
- Roof-mounted chiller replacement
- Refurbishment of four air handling units
- Controls and supporting systems
- O&M manuals and as-installed drawings
The challenge
Delays in plant deliveries were addressed by expanding workforce capacity to maintain the project schedule.
Related services
More projects
If we’re not the right fit, we’ll tell you who is
Project like Marks and Spencer - Watford Cross? Talk to us.
We deliver mechanical and electrical projects from concept to commissioning. Your enquiry goes to our project team. We call back within one working day.