Condition Improvement Fund bids, backed by the contractor who delivers the works
The Condition Improvement Fund (CIF) is the Department for Education’s capital grant for keeping academy, sixth-form college and voluntary aided school buildings safe and in good working order. Rossair supports CIF bids for heating, ventilation, water and electrical projects with the evidence a bid is scored on: a costed options appraisal, a fixed-price quote and a programme built around term dates. If the bid succeeds, our engineers deliver the works. We supported Chichester College’s CIF bid and delivered the funded project.
The mechanical and electrical side of a CIF bid, then the works
CIF bids are scored on three things: project need (55 points), project planning (20 points) and project cost (25 points). Need comes from an independent condition survey. Planning and cost are where most M&E bids lose marks: no real options appraisal, estimates instead of fixed quotes, and a programme that ignores the school calendar. That is the part we build with you and your technical adviser. Under DfE rules the condition survey has to come from a firm that is not quoting for the works, so we work from your surveyor’s report, not instead of it.
- Costed options appraisal for the plant: repair, like-for-like replacement, heat pump or hybrid
- Fixed-price quote with a written commitment to hold the price if appointed
- Electrical load assessment and feasibility for low carbon heating
- Programme planned around term dates, exams and holiday working
- Plant history and failure records from our maintenance logs, for schools we already look after
- Delivery by our own engineers, then commissioning, handover and the health and safety file

What schools need to know about this round
These points come from the DfE’s information for applicants for CIF 2027-28, published in October 2026. Check GOV.UK before you submit, as dates can change.
Key dates
The application window opened on 21 October 2026. New applicants must register for a CIF portal account by 12 noon on 30 November 2026. Applications and all supporting documents must be in by 12 noon on 15 December 2026. Outcomes are expected in May 2027, with appeals from June.
Who can apply
Stand-alone academies, schools in multi-academy trusts with fewer than five schools or fewer than 3,000 pupils, small voluntary aided bodies and sixth-form colleges. Larger trusts and local authorities receive School Condition Allocations instead, and a school gets one or the other, never both.
Project size
Primary and special schools can bid from £20,000. Secondary schools, all-through schools and sixth-form colleges can bid from £50,000. The ceiling is £4 million. The average condition award is around £500,000. Each school can submit up to two projects.
What gets funded first
Compliance and health and safety come first: fire protection, gas safety and electrical safety. Next come critical replacements of coal and oil boilers with low carbon heating where the school could otherwise close. Then weathertightness and keeping heating and water supplies running. On average only about a third of bids succeed.
Commercial heating and boiler replacementCost certainty
To score full marks on cost certainty, DfE expects at least three thorough, fixed-price tenders or quotes, with a firm commitment from each contractor to hold its price. A bid built on estimates scores low. We price CIF quotes to that standard.
Delivery deadlines
Most CIF 2027-28 projects must complete by 31 March 2028. Larger projects can run for up to two years but must finish by 31 March 2029. Heating and plant work is usually programmed into the summer holiday, so the order and lead times need fixing at bid stage, not after the award.
Chichester College: from CIF bid to delivered works
Rossair supported Chichester College’s CIF bid and delivered the funded works. Chichester College is part of Chichester College Group, whose estate we have maintained for over 20 years, including Brinsbury, Haywards Heath, Worthing and Met College Brighton, under one PPM contract. That history matters for a bid: we know which plant is failing, what it has cost to keep running, and how to replace it around a live timetable. The 140kW heat pump installed from stock in 48 hours, and the 2025 HVR Award for Innovative Project, came out of the same relationship.
What a CIF bid is assessed against
- CIF 2027-28DfE’s information for applicants: eligibility, thresholds, scoring and the evidence each bid must include.
- Condition surveyIndependent survey dated no earlier than 1 October 2023, graded A to D for condition and 1 to 4 for priority.
- Options appraisalA costed options appraisal for the specific project is required in every application and is scored.
- CDM 2015Construction (Design and Management) Regulations: client and principal designer duties, and the health and safety file at handover.
- ProcurementTechnical advisers and contractors appointed through a compliant, documented process under the Academy Trust Handbook, with conflicts of interest declared.
- DfE standardsReplacement heating designed to the DfE construction design standards, with energy use modelled for low carbon options.
More for school and college estates
Questions about the Condition Improvement Fund
What is the Condition Improvement Fund?
When is the CIF 2027-28 deadline?
Can a contractor write our CIF bid?
How much CIF funding can a school get?
Can CIF pay for a heat pump?
What happens if our CIF bid is not successful?
Is CIF being replaced?
If we’re not the right fit, we’ll tell you who is